Ms Project - Duration, Start date and Finish date

Was this post useful to you?

Hello, I am preparing plan in MS Project. My question is , all my tasks are Fixed units as resources available time is only 40% of their monthly hours. Now i assigned tasks and added resources with 40% and entered effort. MS Project calculated the duration and set the finish date. if you see below example, if this task takes 25 days to complete then finish date should set to 8/15/14 but it set to 08/1/14. Could you please help me to fix this issue.

Name Work Duration Start Date Finish Date
Draft Plan 80 hrs 25 days? Mon 7/21/14 Fri 8/1/14

Regards,
Venkat