material resources consuming tracking - Microsoft Project

How material Resources consuming can be track by PM ? and who will claim the actual consuming for the materials ? thx in advance...

Results 1 to 9 of 9

  1. #1

    material resources consuming tracking

    How material Resources consuming can be track by PM ? and who will claim the
    actual consuming for the materials ?

    thx in advance



    Diwan
  2. #2

    Re: material resources consuming tracking

    Do you mean "who will claim the consuming" to be the persons using the
    materials? Project attributes the consumption and costs of materials (and
    the labour costs of work resources) to the task that uses them, not to the
    people doing the task.
    --
    Steve House
    MS Project MVP
    Visit http://www.mvps.org/project/faqs.htm for the FAQs


    "Diwan" <com> wrote in message
    newshx.gbl... 
    the 


    Steve
  3. #3

    Re: material resources consuming tracking

    I meant not who will claim the consuming but how the material can be claimed
    if the task that I assigned not to the work resources(people) but only
    material resources?
    and i want to know how to calculate the total cost of materials that have
    been consuming by people?
    FYI, I used my project pro 2002 and project server (PWA) to interact between
    PM and the resources.

    Thank in advance..
    Diwan

    "Steve House" <send.hotmail.com> wrote in message
    news:3f311082$0$12884$com... 
    (and 


    Diwan
  4. #4

    Re: material resources consuming tracking

    Hi Diwan,

    Let me try to simply re-phrase Steve's post.
    There is no link between work resoruces and material reources.
    Material resources are consumed by tasks, not by people.
    HTH

    --
    Jan De Messemaeker
    Microsoft Project Most Valuable Professional
    Project Management Consultancy
    Prom+ade BVBA
    32-495-300 620
    "Diwan" <com> schreef in bericht
    newshx.gbl... 
    claimed 
    between 
    the 
    claim 



    Jan
  5. #5

    Re: material resources consuming tracking

    You have to get over the notion of materials being consumed by resources.
    They are not. Materials are used by tasks, not by people. It sounds like
    you want to get a report that says Bob and Jim are working together laying
    bricks for a wall and Bob laid 100 bricks and Jim laid 150 bricks. Project
    cannot produce that kind of report. It CAN tell you that it took a total of
    250 bricks to build the wall (and the cost of the bricks) but it cannot tell
    you how many of them each bricklayer used. Or have I misunderstood what
    you're asking for?

    --
    Steve House
    MS Project MVP
    Visit http://www.mvps.org/project/faqs.htm for the FAQs



    "Diwan" <com> wrote in message
    news:%phx.gbl... 
    owner/PM) 
    or 
    select 
    list, 
    message 
    the 
    materials 
    to 


    Steve
  6. #6

    Re: material resources consuming tracking

    yup, your explanation is closed to what I'm asking for, steve..
    I'm also agree with ms.project can help us by calculated all materials that
    has being consumed on that task.
    But how to calculate the additional cost of the material that being consumed
    on that task if we at the beginning know exactly the total material being
    prepared for the project ?

    thx in advance..

    "Steve House" <send.hotmail.com> wrote in message
    news:3f38d3e1$0$79063$com... 
    Project 
    of 
    tell 
    by 
    for 
    only 
    not 
    will 


    Diwan
  7. #7

    Re: material resources consuming tracking

    When you create your resources you include the materials you need to track
    in the list on the resource sheet along with the work resources and mark
    them as material under the type column. The unit you use to measure
    consumption is entered in the material label column. If it was movie film
    the label might be "feet", for example, or if it was coal, perhaps "tons"
    etc. The cost per unit is entered in the same standard rate column that you
    use for the labour cost of your work resources. Then when you assign
    resources to tasks, you entered the number of units of materials you
    estimate that task will require in the resource assignment dialog, just like
    you enter the effort percentage of the work resources you're assigning. You
    can enter it as either the absolute amount, ie, 5000 feet of film which will
    remain constant regardless of the task duration, or you can enter it as a
    consumption rate, 500/hour, and it will calculate the total amount based on
    the task duration. So if you were making a movie, a certain task might look
    like this:

    Task:
    Film Car Crash, Duration 3 hours
    Resource Assignments:
    Director 100%
    Camera Operator 100%
    Stunt Driver 100%
    Panavision Camera 300% (meaning we have 3 cameras set up)
    70mm Film 3000/hour (meaning we'll expect to expose about 3000 feet of
    film for each hour of the shoot, 1000 feet per camera, a total of 9000
    unless the duration changes)

    Any of the reports or views that show individual resource costs will show
    the breakdown. Hope this helps

    --
    Steve House
    MS Project MVP
    Visit http://www.mvps.org/project/faqs.htm for the FAQs

    "Diwan" <com> wrote in message
    news:%phx.gbl... 
    that 
    consumed 
    resources. 
    like 
    laying 
    total 
    consumed 
    message 
    resources 
    be 
    that 
    interact 
    using 


    Steve
  8. #8

    Re: material resources consuming tracking

    Steve,

    your explanation is really help for me to know better how the material
    resources can be proccess in ms.project.Thanks steve..

    could you give me another sample for that process. e.g : in manufacturing
    industry maybe? I reallly want to know how ms.project handle project in
    manufacturing industries, so ms.project features might be usefull for them?

    Thanks in advance..
    Best Rgrds,

    Diwan

    "Steve House" <send.hotmail.com> wrote in message
    news:3f3a46a3$0$15204$com... 
    you 
    like 
    You 
    will 
    on 
    look 
    being 
    cannot 
    what 
    spent 
    the 
    resources. 
    can 
    but 
    them, 
    who 


    Diwan
  9. #9

    Re: material resources consuming tracking

    There are so many possibilities I can't begin to think of one that would
    cover all the bases. You say you are interested in an example from
    manufacturing and my alarm bells are going off - what exactly are you trying
    to get Project to do for you? Can you describe the substance of your
    specific project in more detail please? Are you trying to schedule a
    production line or are you trying to get a new product online line, setup
    the assembly line etc. Project is not a optimal tool to use for ongoing,
    continuous operations like scheduling shift work on an assembly line putting
    together toasters one after another ad infinitum. OTOH, it is great tool to
    use to schedule the development project that creates the new Nuclear Powered
    Super-Megatoaster that Marketing wants to put in the stores next year and
    building the new plant that will manufacture it.

    --
    Steve House
    MS Project MVP
    Visit http://www.mvps.org/project/faqs.htm for the FAQs


    "Diwan" <com> wrote in message
    newshx.gbl... 
    them? 
    track 
    film 
    "tons" 

    of 
    show 
    message 
    sounds 
    menu 
    materials 
    in 


    Steve

Similar Threads

  1. unread material in views - Groove 3.1
    By msnews.microsoft.com in forum Microsoft Groove
    Replies: 4
    Last Post: 09-06, 03:23 PM
  2. tracking web sites
    By Tere01 in forum Internet Explorer 6, 7, 9
    Replies: 2
    Last Post: 08-23, 01:47 PM
  3. Project VBS Reference material
    By S in forum Microsoft Project VBA
    Replies: 2
    Last Post: 09-26, 06:44 PM
  4. URGENT!! material usage again!!
    By Matt in forum Microsoft Project
    Replies: 2
    Last Post: 08-29, 07:21 AM
  5. material resource BCWP
    By Stressed in forum Microsoft Project
    Replies: 0
    Last Post: 07-10, 08:39 PM

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100