Assigning Unique ID predecessors in MS Project VBA

Was this post useful to you?

Hi,

I am trying to create a macro for MS Project for assigning relationships to tasks using their unique IDs in Unique ID Predecessor. I need to use unique ids as tasks are deleted or added occasionally in my master schedule (consisting of sub projects)
I use the following syntax to link tasks
SetTaskField Field:="Unique ID Predecessors", Value:="1FS", TaskID:=2
But it is not useful if new tasks are inserted or deleted as task ids change. So i want use unique task ids

Thanks!!